From: Thistle, Wayne [WThistle@GOV.NU.CA]
Sent: Wednesday, August 02, 2006 12:32 PM
To: marc@mosher.ca
Cc: Dave Mosher; Phillis Beaulieu; Hanley, Bob; Ruediger, Ralph
Subject: RE: Rankin Inlet Heat Distribution - Request for Water Usage for Hydrostatic Testing and Flushing

Hi Marc;

Use of the Rankin Inlet Water Supply for testing piping is approved provided all rules and regulations by the government departments having jurisdiction are follow in regards to the use off and disposal of water used for pipe testing purposes.

1.      Obtain approval of governing agencies before discharging water into storm, sanitary or other receiving systems.
2.      Co-ordinate flushing of piping with the Dept of Community & Government Services, O&M division and Fire Department personnel. Do not cause loss of fire storage in reservoir at any time.

3.      Follow all procedures outline in your contract documents for this procedure.
4.      Provide CGS a copy of the Section in the contract specifications applying to Hydrostatic testing, flushing of pipes, & disposal of water for review.

If you have any questions please contact me at your convenience.

Regards,

Wayne

Wayne Thistle, CET

Project Officer

Dept. of Community & Government Services

Kivalliq Region, Government of Nunavut

PO Bag 002, Rankin Inlet, NU, X0C 0G0

Phone # (867) 645-8178

Fax # (867) 645-8196