From: David Hohnstein
[Tech2@nwb.nunavut.ca]
Sent: Thursday, November 10, 2005 9:43
AM
To: Ken Weagle
Cc: Phyllis Beaulieu
Subject:
Spill Contingency Plan NWB2FOR0406
Good morning Ken,
going by the series of emails that finally found
its way to you, I hope you are the one to be checking with on this Licence Spill
Contingency Plan.
I had this plan passed onto me from Phyllis
yesterday (see email below), and looking back at the licence, under Part G, Item
1, the licensee was to submit an "addendum" or addition to the conditionally
approved Spill Plan that was to address the six items listed. These items
were not addressed in the Plan that was submitted with the email below and
remain outstanding.
Not sure why the Spill Report Form was listed under
Part G, Item 1, as it was in the original submission (maybe it didn't print off
or something!!), but the others are still valid and are required to be updated
for the Plan prior to receiving final approval of the Plan.
Also, if submitting a complete Plan, please
identify which items have been updated, as well as a revision date on
the Plan.
Thanks again, if you have any questions on the
above or the plan itself, feel free to give me a call at your
convenience.
Regards,
____________________________________
David Hohnstein,
C.E.T.
Technical Advisor Mining
Nunavut Water Board
P.O. Box
119
Gjoa Haven, NU X0B 1J0
Office Phone: 780.443.4406
Office Fax:
780.443.4080
----- Original Message
----------------------------------------------------------------
Sent: Thursday, November 10, 2005 9:14 AM
Subject: FW: Spill Contingency Plan NWB2FOR0406
Here
is the email that came with it
________________________________
Phyllis Beaulieu
Manager
of Licensing
Nunavut Water Board
P.O. Box 119
Gjoa Haven, NU X0B
1J0
Phone: (867) 360-6338
Fax: (867) 360-6369
E-mail: licensing@nwb.nunavut.ca
Dear Phyllis;
I'm sorry about this over sight. The
plan was written in May 2004 and I was fairly sure it was submitted with the
original application. Here it is again for your
records.
Cheers
Ken Weagle
EBA Engineering Concultants Ltd.
for
Martin Knutson
-----Original Message-----
From: Martin Knutson [mailto:mknutson@matrixhelicopters.com]
Sent:
Thu 10/13/2005 8:04 AM
To: Ken Weagle
Subject: Fw: Spill Contingency Plan
NWB2FOR0406
----- Original Message -----
From: "NWB Manager of
Licensing" <licensing@nwb.nunavut.ca>
To: "Neil Willoughby"
<neilwilloughby4@hotmail.com>; "Martin
Knudson"
<mknutson@matrixhelicopters.com>
Sent: Wednesday, October
12, 2005 5:59 PM
Subject: Spill Contingency Plan
NWB2FOR0406
>
> Further to my email to Neil on June 25,
2005, please be advised that we
have
> still not received the updated
spill plan required under the terms and
> conditions of your current
license. We would appreciate a response as soon
> as
possible.
>
> ________________________________
> Phyllis
Beaulieu
> Manager of Licensing
> Nunavut Water Board
> P.O.
Box 119
> Gjoa Haven, NU X0B 1J0
> Phone: (867)
360-6338
> Fax: (867) 360-6369
> E-mail:
licensing@nwb.nunavut.ca
>
>
>