Hi Rick - Point #10 refers to the response providing for Stream C3 - Extent of water quality impacts.
Derrick
-----Original Message-----
From: Rick Pattenden
[mailto:rpattenden@mainstreamaquatics.ca]
Sent: Tuesday, November 23, 2004 7:36 PM
To: Derrick Moggy
Cc: Greg
Missal
Subject: DFO email dated 23 November 2004
Derrick:
I have reviewed your email dated 23 November 2003 and have the
following
comments.
Point #8
- Water temperatures will be
compared to background levels
(pre-development).
- The water flow station will be located upstream of the
berm during
pre-developmnent monitoring.
- Once the diversion is activated the berm will no longer have
an effect
and the station will be re-positioned to
Diversion Pond #2.
Points #10
- Please indicate which
section of the Mainstream summary memo this
point refers
to.
Point #11
- The Stream C3 mitigation
plan will be implemented prior to the
discharge of water
from Long Lake/PKCA.
- The mitigation plan will include
evaluation by a qualified
hydrologist.
- This will be followed by a monitoring program that will be
sufficient
frequency to ensure early detection of
erosion.
Point #12
- Tahera will continue to
develop the revised NNLP so that the DFO
authorization
can be issued in a timely fashion.
- Please note that
some components of the revised plan cannot be
finalized
until the NWB hearings are complete.
Regards,
Rick Pattenden, M. SC., P. Biol.
Principal, Senior Biologist
Mainstream Aquatics Ltd.
6956 Roper
Road
Edmonton, Alberta
T6B
3H9
P: 780-440-1334
F: 780-440-1252
C: 780-919-2317
Email:
rpattenden@mainstreamaquatics.ca
---
Outgoing mail is certified Virus
Free.
Checked by AVG anti-virus system (http://www.grisoft.com).
Version: 6.0.786 / Virus Database: 532 - Release Date:
10/29/2004