From: NWB Senior Technical Advisor [srtech@nwb.nunavut.ca]
Sent: Wednesday, July 23, 2003 2:25 PM
To: Phyllis Beaulieu
Subject: Fw: Proposed Road Construction
Phyllis also discussed with Jack Kaniak yesterday that so long as HBJV does not exceed the 150 cu.m/day maximum water use for the whole site, no amendment would be required under the water licence.  See below on email sent to Hugh Wilson re: road construction. If you have any questions let me know.
Hope this helps Jorgen.
_______________________
Dionne Filiatrault, P. Eng.,
Senior Technical Advisor
Nunavut Water Board
P.O. Box 119,
Gjoa Haven, NU   X0B 1J0
Tel: (867) 360-6338
Fax: (867) 360-6369
email: srtech@nwb.nunavut.ca
----- Original Message -----
From: NWB Senior Technical Advisor
To: Hugh R. Wilson
Sent: Tuesday, July 22, 2003 10:28 AM
Subject: Proposed Road Construction

Hugh   
Further to our telephone conversation regarding proposed road construction to access drilling site at the Boston camp.  Provided there are no stream crossings requiring culvert installation and the proposed road alignment is outside 30 m setback of the high water mark of a water body no changes/amendments are required to the NWB Licence NWB1BOS 0106.  If you require further clarification do not hesitate to contact me.
Regards,
Dionne
____________________________
Dionne Filiatrault, P. Eng.,
Senior Technical Advisor
Nunavut Water Board
P.O. Box 119,
Gjoa Haven, NU   X0B 1J0
Tel: (867) 360-6338
Fax: (867) 360-6369
email: srtech@nwb.nunavut.ca