November 22,
2005
David:
I have received the various emails
that you sent the other day outlining the changes that need to be
addressed.
Prior to my leaving town for
With regards to the Amended
Application form that was submitted to the NWB on our behalf by RESCAN
Environmental Services, it should be noted that the objective of this
application is to make changes to our present permit so as to allow for a camp
move from the present Ferguson Lake Lodge which we are leasing from Keith Sharp
of Rankin Inlet. As a result of certain issues that have been brought to our
attention, we are having to move to a new location. This location is distal to
the main Ferguson Lake Lodge area and becomes a wholly controlled camp of
Starfield Resources. Land leases for the new camp have been applied for with the
local KIA officials which we are currently awaiting approval. However, due to
the nature of the camp location and also the fact that we will be building the
camp, we are having to use the Ferguson Lake Lodge as a base until our new camp
is built. This is reflective in the application submitted by RESCAN which
indicates that the present camp will be ongoing. As a result Starfield Resources
will continue to occupy the Ferguson Lake Lodge until such time as the new camp
is built with the upgraded features as outlined in the
submittal.
Hopefully this clarifies on or two
issues that you had brought up in the email. As with the other issues, I will be
talking to Latisha and also Francois today (RESCAN) with regards to certain
other areas that need to be addressed. It should be noted that RESCAN has been
appointed as our Environmental Consultants and in conjunction with myself, will
be handling future permitting issues. If there are any questions in the matter,
I can be reached in camp at (604) 515-0398 and or by email at sfield@skycomip.com or john_nicholson@telus.net
Sincerely,
John Nicholson
PGeo
Project
Manager
Starfield
Resources