Hello:
The only change to the application
package is the inclusion of drilling. In the Abandonment and Restoration
Plan drilling activities have been included. Under Seasonal Shutdown and
Final Abandonment and Restoration, we have included how drill sites will be
cleaned up and restored where necessary. As well, the drill sites will be
documented (before and after photos) for reporting.
In the Spill Contingency Plan, we
have included the MSDS sheets for products that will or may be used for
drilling. The original Spill Contingency Plan already contained spill
response actions for these products. As the original application, which
was withdrawn last spring, included drilling, the Spill Contingency Plan was
written to include all spill response actions.
If you have any other questions,
please do not hesitate to contact me.
Thanks,
Allison